2019 FISH SPAWN
PROJECT PRINCIPLE FISH SPAWNING PERIOD FOR OPERATIONAL CONSIDERATIONS 1 OPERATION START DATE TARGET STARTING ELEVATION DESIRED MINIMUM OPERATIONAL ELEVATION END OF 4 WKS ENDING DATE CURRENT STATUS
LANIER (BUFORD) 01 April - 01 June 04 May 1071.80 1071.30 01 June TBD Ongoing
WEST POINT 01 April - 01 June 26 April  633.20 632.70 24 May TBD Ongoing
GEORGE 15 March - 15 May 22 March 188.21 187.71 19 April TBD Ongoing
SEMINOLE (WOODRUFF) 01 March - 01 May 14 March  76.91 76.41 11 April 11 April Complete
APALACHICOLA RIVER  01 April - 01 June     WCP     Continuous*
ALLATOONA 15 March - 15 May 24 April 839.28 838.78 22 May TBD Ongoing
OKATIBBEE 01 April - 01 June 01 April 339.10 338.60 29 April 28 April Complete
     
1. The goal is to manage the reservoir or river conditions for 4-6 weeks within this 8 week period, if conditions allow. 
       Steady lake levels may be impossible to achieve during floods and droughts.
* Following the  Water Control Manual Plan (WCP) and the Biological Opinion issued by the FWS