2/10/2012              
Mobile District Corps of Engineers Tentative Hydropower Generation Schedules
CENTRAL STANDARD TIME, GENERATION SHOWN IS MEGAWATTS  
   
note: generation schedules are subject to change at any time without notice.  
   
  ALLATOONA BUFORD CARTERS WEST POINT W.F. GEORGE R.F. HENRY MILLERS FERRY
2/10/2012              
  SCH SCH SCH SCH SCH SCH SCH
00:00 - 01:00 2 5 0 3 0 40 56
01:00 - 02:00 2 5 0 3 0 40 56
02:00 - 03:00 2 5 0 3 0 40 56
03:00 - 04:00 2 5 0 3 0 40 56
04:00 - 05:00 2 5 0 3 0 40 56
05:00 - 06:00 2 5 241 3 120 40 82
06:00 - 07:00 2 59 520 45 120 82 82
07:00 - 08:00 2 5 381 45 120 82 82
08:00 - 09:00 2 5 241 3 120 82 82
09:00 - 10:00 2 5 0 3 120 46 82
10:00 - 11:00 2 5 0 3 0 0 0
11:00 - 12:00 2 5 0 3 0 0 0
12:00 - 13:00 2 5 0 3 0 0 0
13:00 - 14:00 2 5 0 3 0 0 0
14:00 - 15:00 2 5 0 3 0 0 0
15:00 - 16:00 2 5 0 3 0 0 0
16:00 - 17:00 2 5 0 3 0 0 0
17:00 - 18:00 2 5 120 3 60 20 0
18:00 - 19:00 2 5 120 3 68 54 48
19:00 - 20:00 2 5 120 3 60 54 48
20:00 - 21:00 2 5 0 3 56 30 48
21:00 - 22:00 2 5 0 3 56 30 54
22:00 - 23:00 2 5 0 3 0 40 56
23:00 - 24:00 2 5 0 3 0 40 56
TOTAL 48 174 1743 156 900 800 1000
               
Buford Powerhouse Generation Schedule Recording:  (770) 945-1466
West Point Powerhouse Generation Schedule Recording:  (706) 645-2929
W F George Powerhouse Generation Schedule Recording:  (866) 772-9542 ext. 244
Allatoona Powerhouse Generation Schedule Recording:  (706) 334-7213
R F Henry and Millers Ferry Powerhouse Generation Schedule Recording:  (334) 682-4896